SD Projects

TM Rural Water Distrist
Dolton, SD
 
 

15,000 Sq. Ft. Water Treatment Plant – 4 MGD capacity.  Cast in place/ Pre-cast Concrete construction

Lime softening/ Carbon Dioxide/ On-Site Chlorine generation/ Solids Contact Clarifier/ Gravity Filtration
750,000 gallon cast in place ground storage reservoir
 

 
WWTF Improvements - Phase IIA
 Aberdeen, SD
 
 
Setting Precast Walls
 

Contract:  $1,186,600.00

Completion:  January, 2008

Scope:  Expansion of existing Wastewater Treatment Plant consisting of erection of a precast building to house soda ash feed equipment complete with indoor storage silo and associated process, monitoring, and control equipment.


 
Big Sioux Community Water System
 
500,000 Gallon Clearwell Addition Project
Egan, SD
 
 
 
Setting Wall Gang Forms
 

Contract:  $734,000.00

Completion:  September 2007

Scope:  Construction of 500,000 gallon below grade clearwell with associated system tie-ins.